• Study Commencement (June 2013)
  • Detailed Design and Environmental Assessment documented in an Environmental Screening Document (ESD) for MTO internal use in January 2014
  • Environmental Clearance to proceed to construction (January 14, 2014)
  • Construction was initiated in the spring of 2014 and completed in the fall of 2015