• Detailed Design and Environmental Assessment documented in an Environmental Screening Document (ESD) for MTO internal use in January 2015
    • Environmental Clearance to proceed with construction (January 2015)
    • Construction was initiated in the spring of 2015 and completed in the fall of 2016